Cap beam is slated to start next week. Then they have to excavate down roughly 50’ And install earth support. It’s going to be a while before this one pokes its head up above ground.
Waterproofing starts Thursday. Crane going up this weekend. Formwork starts Monday. Lagrange has a caisson foundation system due to poor ground conditions.
inherently slower than a Mat on virgin ground.