These probably are not actually timber, typically an engineered composite plastic that can look like timber. They have longer life cycles because they won't crush, split, or decay; better strength than timber, and are able to absorb impacts and deflect then return to their original position.
Not only does Tower A have widespread asbestos, it's also at the end of its useful lifespan. Re-use would have required all of the visible exterior to be removed/destroyed just to be able to sandblast the steel.
I believe the plan is to at least preserve and display the cast stone "Boston &...
There are something like 800+ OCS poles along both branches of the extension. A portion are mounted on top of foundations with a base plate, but the vast majority are set inside drilled shafts (you can see both in the photos above). The poles mounted on base plates should be pretty consistent...
They're dealing with a very narrow corridor from right-of-way constraints where fitting fencing and OUC poles between the commuter and light-rail came down to fractions of an inch.
I believe the modular wall was originally planned for the other side of the path next to the ROW, but there were some issues that required they move it and prop up the path instead. By that time the track retaining wall was already in place.
I walked from sullivan square station to that office at the end of innerbelt road many times.
I think I would consider those to be culverts - they're just not for water in this instance.
Those are inverted T-Walls. The "corrugated things" are the stems for each T-Wall block and they interact with the (future) backfill through friction to produce a resistance to the earth pressure that's on the back face of the panel. It's the same concept as other mechanically stabilized earth...
The CR and GL have different requirements for horizontal and vertical curves, as well as clearance under bridges, etc. I'm sure they tried keeping the adjacent lines as close in elevation to each other as possible, but curb walls inevitably were required.. especially considering the need for...
They actually are for OCS support. There are several retaining wall soldier piles on the green line side of the main corridor that will also support OCS as well.