It is so wild how this demolition project looks more like a construction project.
It is so wild how this demolition project looks more like a construction project.
Has anyone timed out the demolition rate on the old Volpe? Is it going to be all done by the end of 2026?
Don't know, but I might guess it is about to speed up.Has anyone timed out the demolition rate on the old Volpe? Is it going to be all done by the end of 2026?
- Tower building high-reach demolition preparation activities will start. Removal of the formwork/scaffolding climbing system at the top of the building and the hoist (external construction elevator) on the east side of the tower building in the center of the property will begin....- Debris, window frame and equipment removal to prepare for high reach demolition at the tower building.
Cool. This jibes with that they are saying in the construction updates thread about switching demolition modes