The high-level platforms that are planned for the Haverhill Line will be shorter than 800 feet:![]()
MBTA receives nearly $140 million grant for Haverhill Line improvement - The Boston Globe
The MBTA will also upgrade the Reading, North Wilmington, Ballardvale, and Andover stations with high-level platforms, improving accessibility.www.bostonglobe.com
According to an MBTA spokesperson, “the plan for all four stations (at Andover, Ballardvale, North Wilmington, and Reading) is to have two-sided, short high-level platforms. They will not be full-length (not 800 feet), but they will be accessible.”
The project will be split into two phases, with the first breaking ground in 2028 and the second breaking ground in 2029:
A project schedule from the MBTA’s grant application suggests that these improvements could be in place by 2030.
The grant application suggests that the work will proceed in two phases. Phase 1 would begin construction in early 2028, and the shorter segment of double-track from Lowell Junction through Ballardvale, plus the construction of new high-level platforms at Ballardvale and Andover stations.
“Phase 2” would begin construction in 2029, and includes the longer section of double-track from Reading to Wilmington Junction (where the Haverhill Line intersects with the Wildcat branch line) and the new high-level platforms at Reading and North Wilmington stations.
The Tewksbury Street grade crossing will be eliminated as part of the first phase: