  1. The EGE

    MBTA Construction Projects

    Curious to see if that comes true. The website said "January 2026" until at least February: https://web.archive.org/web/20260208142953/https://www.mbta.com/projects/franklin-line-double-track
  2. The EGE

    General MBTA Topics (Multi Modal, Budget, MassDOT)

    1975 2026 2026 change B Branch: Boston College to Park Street 35 minutes 45 minutes +10 minutes (+29%) C Branch: Cleveland Circle to Park Street 23 minutes 35 minutes +12 minutes (+52%) D Branch: Riverside to Park Street 43 minutes 48 minutes +5 minutes (+12%) Red Line: Quincy Center to...
  3. The EGE

    Local Politics Thread

    The site isn't amazingly transit-accessible - the adjacent 217 gets a few trips a day, the 210 (planned for 25 peak / 50 midday and weekend) is 8 minutes walk, and Wollaston station is 13 minutes walk. Neither is there particularly good auto access. The buildings are generally nice-looking, if...
  4. The EGE

    MBTA Construction Projects

    Cool spot! That looks to be the east staircase; I spotted the south one during street construction in 2015. Information is sketchy, but it appears the two were replaced with the current entrances when the Symphony towers were built in the mid-1970s.
  5. The EGE

    MBTA Buses & Infrastructure

    My previous thoughts (just from descriptions) here. My revised thoughts from this information (all images are 2019 / current proposal / new proposal): 465 to Danvers Square: this continues to look good. I like the tighter loop in Danvers, and retaining service on Margin is interesting. (This...
  6. The EGE

    General MBTA Topics (Multi Modal, Budget, MassDOT)

    I would assume that World Cup preparations are consuming all available service planning resources.
  7. The EGE

    General Massachusetts Politics Discussion

    I have to wonder how much of the outward migration, especially at the lower end of that $200k+ range, is due to housing costs. That's going to be a much larger financial consideration for the majority of that range than the tax.
  8. The EGE

    Red Line Extension to Arlington Heights

    There's no way that survives a cost-benefit analysis, for a number of reasons. Because the existing tunnel goes all the way to Thorndike Park, building the tunnel under Mass Ave would add about 0.6 miles of additional tunneling. The Minuteman has minimal buried utilities, and there are...
  9. The EGE

    MassDOT Rail: Springfield Hub (East-West, NNERI, Berkshires, CT-Valley-VT-Quebec)

    The Hoosac, rather infamously, took 25 years and >100 lives to be completed. A significant part of that was the geological conditions, including water-logged rocks that don't hold shape well. Even with modern equipment, as F-Line indicated, it would still be a very difficult tunneling job. The...
  10. The EGE

    General MBTA Topics (Multi Modal, Budget, MassDOT)

    In 1924 (approximately the peak of service) most of the Owl services operated hourly. A few had half-hour service; some were irregular. https://commons.wikimedia.org/wiki/File:1924_BERy_night_cars_timetable.pdf
  11. The EGE

    MBTA Buses & Infrastructure

    In 2018, about as many riders on the 22 stayed on past Jackson Square as got off: https://cdn.mbta.com/sites/default/files/projects/betterbus/route-profiles/22.pdf With BNRD, the 22 will turn west at Roxbury Crossing to go to the LMA. That will probably increase the number of riders riding past...
  12. The EGE

    MBTA Buses & Infrastructure

    Arborway Garage design contract at tomorrow's MBTA Board meeting: https://cdn.mbta.com/sites/default/files/2026-04/2026-04-30-arborway-design-mbi-contract-v3.pdf Five and a half years including construction phase, which puts the new garage opening around late 2031.
  13. The EGE

    🔷 Open Thread

    I'm finally moving back to the Boston area - which means I have to figure out getting an apartment cross-country. Looking for advice on how to go about it (here on in DMs). We're aiming for the Davis/Porter area, probably a 2 bedroom, moving in July 1. How far ahead do apartments tend to be...
  14. The EGE

    Everett Transportation (SL3 extension, potential OLX/GLX, Sweetser Circle infill station)

    That would prevent it serving downtown Chelsea, and would leave Central Avenue without frequent service.
  15. The EGE

    Regional New England Rail (Amtrak & State DOT & NEC)

    Trainsheds are back, baby! It's quite the change; I don't hate it, but it's honestly a bit disappointing. First thoughts: Visually it's a great concept ; there's nothing at platform level that's historic (or pretty), and it goes well with the station building. Much better than the parking...
  16. The EGE

    Redesign the Urban Ring

    Slight correction to this: In 1946, the legislature directed the Coolidge Commission to consider a "a subway loop from Boston through Everett, Maiden, Medford, Somerville and Cambridge to Boston and to Forest Hills in the West Roxbury district". That would have been a rather ungainly route...
  17. The EGE

    Gillette Stadium Transportation Improvements

    World Cup service changes are out: https://www.mbta.com/service-changes/service-changes-during-the-world-cup General service reductions for five weeks, including fewer express trains and short turns. No East Taunton shuttle trains. On match days, Foxboro has shuttle buses for the outer...
  18. The EGE

    Redesign the Urban Ring

    Ultimately, I'm not sure that the radial-circumferential combo works well here. A circumferential line is primarily for short-distance trips and connecting places to the radial lines; if you're going far around (such as Chelsea-LMA) it'll be faster to go through the core. Everett riders have to...
  19. The EGE

    Green Line Extension to Medford & Union Sq

    I don't believe a tunnel was ever seriously proposed. Because of the number of tracks, it would be a 200+ foot tunnel with lengthy approaches. There's definitely an element of a bridge feeling safer than a tunnel. The Community Path is on an embankment to the north (the tracks originally crossed...
  20. The EGE

    Site Issues

    Weirdly, I get a "method not allowed" error when using a VPN (built-in Firefox VPN) but the site works fine without.