matredsoxfan
Active Member
- Joined
- Apr 7, 2013
- Messages
- 337
- Reaction score
- 0
I just assumed they were waiting for the northbound side overpass to be completed before shifting all of the 109 traffic onto the new overpasses before demolishing the old ones and rebuilding them.
The project design calls for 5 full travel lanes in each direction between Highland Ave and route 9, not sure how they're going to squeeze two additional travel lanes in on that stretch.
I also feel like they'll start work on one piece, work on it for a couple of weeks and then move and and start something else before they finish it.
First 109: Once the new bridge over the Southbound lanes is completed traffic will be shifted to those new bridges and the old bridges demolished. The don't want to open the lanes yet as it would be a zig zag configuration going from new bridge over Northbound and then shifting back to the old bridge over Southbound.
Second: The road will not be 5 lanes between Route 9 & Highland Avenue. The road will be 4 lanes each direction with a full breakdown lane. Collector distributor roadways will be built both Northbound & Southbound between Highland Avenue and the new interchange at Kendrick Street.