Summary of Project Changes
As presented in the 2013 EPNF, the Project was a mixed-use development with a
304-unit residential apartment building, a hotel building with 247 guest rooms, a
three-level underground parking garage with 640 striped spaces, public open spaces
connecting the two buildings at the ground and terrace levels, and a mix of
restaurant, retail and office spaces.
As described further below, changes to the Project are limited to: (1) an increase in
the number of hotel rooms (from 247 to 293); (2) a decrease in the number of
underground parking levels (from three to one) and parking spaces as described
herein; (3) certain design changes within the previously approved building
envelopes as described herein; and (4) possible revisions to the affordable housing
program for the Project to ensure the Project’s financial feasibility.
Hotel Room Change.
The number of hotel rooms will be increased by 46 within the
previously approved building envelope to a total of 293 guest rooms. The
Proponent, working with the proposed hotel operator, determined that a modest
increase in the room count is a desirable alteration to the Project. The increase in
room count has been accommodated within the previously approved building
envelope by using smaller guest room dimensions and through the repurposing of
interior spaces.
Parking Change.
The underground garage has been redesigned to reduce the
parking from 640 striped parking spaces on three levels, to a maximum of 420
parking spaces on one level. An initial 197 striped parking spaces will be provided
on the single parking level, with the Proponent having the ability, at its sole
election, to increase the capacity of the garage to a maximum of 420 parking spaces
through the installation of mechanical car-stacking machinery and/or through
managed valet operations upon the Proponent’s determination that an increase is
necessary to accommodate the needs of the Project or the CFDA. The Project’s
Traffic Engineer has evaluated the current and proposed parking, and determined
that the reduced parking is sufficient for the Project.
Additional parking for the CFDA is being created through Massport’s South Boston
Waterfront Transportation Center.
Design Change.
When the 2013 EPNF was submitted, both buildings were designed
with eleven occupiable floors, with the twelfth floor of each devoted primarily to a
mechanical penthouse, housing the cooling towers, mechanical and electrical
equipment, generators and energy recovery units. At the hotel, this twelfth floor
had a small amenity space for the hotel, labeled as a "Hotel Sky Bar", while the
twelfth floor of the residential was not counted as an occupiable floor. The office
component included approximately 14,400 square feet of office space located
between the hotel and residential uses on the ground level of the Project. Retail
spaces included approximately 17,900 square feet of retail and restaurant located at
the street and terrace levels.
As a result of the modifications to the Project, the interior layout of both buildings
has evolved to make the twelfth floor of both buildings occupiable. At the hotel, the
area devoted to amenity spaces has been increased to add a small fitness room and
pool, with the area devoted to mechanical equipment reduced. At the residential
building, the mechanical penthouse on the twelfth floor has been reduced and
shifted away from Northern Avenue, allowing an amenity space with a pool,
clubroom, and outdoor roof deck overlooking the corner of Congress Street and
Northern Avenue. These modifications do not alter the overall building massing as
previously approved.
Affordable Housing. The Proponent also seeks modifications to the on-site
affordable housing1 to be provided as required in order to insure the Project’s
financial feasibility while in compliance with the Mayor’s Inclusionary
Development Policy.
Adjustments to the Project Schedule
The schedule for the Project as presented in the 2013 EPNF was for the completion
of permitting in the third quarter of 2014, with construction following shortly
thereafter. Construction was anticipated to be completed within eighteen to twentyfour
months. However, due to complications in identifying an appropriate hotel
operator and the financial feasibility of the Project as described in the 2013 EPNF,
permitting and development has been delayed.
Given the above, the current schedule for the commencement of construction is
March of 2017, with an estimated completion date of July 2019.