Red Line delayed by smoke, signal problems after MBTA touts "successful" 10-day shutdown for repair work
The Red Line is back open after a 10-day shutdown for repairs, but Boston-area MBTA riders weren't going anywhere fast on Friday.
At 10:45 a.m., the T posted that there were delays of about 15 minutes due to a disabled train at Harvard and said trains may stand by at stations. The agency said at 11:23 a.m. that the delay had cleared.
But problems returned in the afternoon. The T said at 2:30 p.m. that a signal problem near Harvard was delaying trains for about 15 minutes. At 3:39 p.m., the T said delays had grown to 20 minutes due to the ongoing signal problem near Harvard and reports of smoke at the Charles/MGH station.
As of 5 p.m., the Red Line delays had grown to 25 minutes as crews worked to resolve the signal problem.