New England Electrical Grid

When the New England Clean Energy Connect transmission line started carrying electricity from Canada into Maine in January, supporters hailed the project as a triumph for renewable power. Now, after nearly six months of operations, the early numbers raise questions about whether the project will be able to advance the region’s energy transition as much as advertised.
Energy flow into New England is up just marginally, and there have been roughly 27 days when no power at all traveled along the new line, commonly called NECEC. If current trends hold, New England will receive less hydropower this year over two transmission lines than it did over just one line in 2023 and previous years.
“What we’ve seen so far is not what some people expected to see,” said Joseph LaRusso, manager of the Clean Grid Program at climate nonprofit Acadia Center. Potentially putting further strain on the supply of Canadian hydropower is the Champlain Hudson Power Express, a transmission line that started sending electricity from Quebec into New York City this month.
[...]
The operations have not had the smoothest start. NECEC was completely inactive for several spans — from a half day on April 28 to nearly two weeks at the end of May and beginning of June. The most recent outage was due to “technical difficulties,” Hydro-Québec spokesperson Lynn St-Laurent said in a written statement.
“Once repairs were completed, deliveries resumed,” she said. “With any new transmission infrastructure, a period of optimization and fine-tuning is to be expected.” Still, most of the time, hydropower has flowed steadily on the new infrastructure. Through the end of April, Hydro-Québec exported about 2.4 terawatt-hours of power on the transmission line.
 
It doesn’t help that the grid is constrained shipping electricity between Maine and NH. ISO-NE has an RFP out to fix that, but the in service dates for that work is 2032+.
 
It seems that drought conditions have left Hydro-Quebec with less surplus electricity to sell to New England. That doesn't mean that NECEC wasn't a sound project. There's only a half a year's worth of data available. I think it's inevitable that more rain will mean more Canadian energy coming onto the New England grid.

I agree that the RFP to address the bottleneck in Maine would also be a plus. It would have the benefit of the potential to move more northern Maine onshore wind power to southern Maine and New Hampshire. From what I understand this project would require upgrading existing lines and substations rather than constructing new lines in environmentally challenging areas.
 
Progress on our wind energy projects. Through further buildout of Revolution Wind, complete commissioning of Vineyard Wind (or both) mixed with good offshore wind speeds, the grid set a new record today of ~2GW of peak generation this afternoon. This is a new record and at some points during the day was producing >15% of total load. It's pretty warm today so likely some strong AC loads, but a cool breezy fall day could push marginal prices negative now that capacity is so high. Doubling or tripling this amount of wind capacity would absolutely redefine energy generation in New England. Nuclear is out (from above) but a bit more baseload capacity from imported hydro would really start to shave that marginal need for combustion on the grid.

1789068242914.png


1789068329772.png
 

Back
Top