Northeast Corridor 2035 (Amtrak & State DOT & NEC)

bigeman312

Senior Member
Joined
Jul 19, 2012
Messages
1,653
Reaction score
299
For the Acela, there's now a good list at the Connect NEC 2035 project site:
Where they seem to say there's about an hour's worth of time to be saved between Boston and NYC, (about half between BOS & NHV and the other half between NHV and NYP)
Amazing link. For those who didn't click the link, here are the "NE Special Project Highlights"

NE Special Project Highlights
  • Massachusetts Third Track (Readville to Canton): This project supports additional service in the NE territory by adding a third track between Readville and Canton Junction stations. Eliminating the two-track configuration in the area will mitigate an existing capacity bottleneck for Amtrak and MBTA services.
  • Pawtucket/Central Falls Station: The new Pawtucket/Central Falls Station will provide communities located between Providence, RI and Attleboro, MA with access to commuter rail service. This station will provide relief to overcrowded stations in Providence and South Attleboro, while attracting new riders from adjacent residential redevelopment areas that will take advantage of proximity to transit for access to jobs, educational opportunities, and medical options in Boston, MA and Providence, RI.
  • Fitter Interlocking: This project will include the construction of a new universal interlocking on SLE in Clinton, CT that will divide a 16-mile interlockingto-interlocking segment (Guilford and View Interlockings) into two shorter segments, improving reliability by allowing single track operation over shorter segments during maintenance with less operational disruption.
  • SLE Grade Crossing Elimination Projects: Four of the eleven remaining grade crossings on the NEC will be eliminated, minimizing the risk of train-vehicle collisions and delays caused by grade crossing warning device malfunctions.
  • New Haven to Providence Capacity Planning Study: Study of investment options to improve capacity and service performance between New Haven, CT and Providence, RI.
 

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,055
Reaction score
1,343
Let's discuss the "Connect NEC 2035" Plan here, since it is essentially the Biden Era reboot of earlier States+Amtrak plans for the NEC, but this time the states are more engaged.

CONNECT NEC 2035 (C35) is a 15-year plan representing the most ambitious reinvestment program in the NEC’s history and a new way of planning: a multi-agency, multi-year, shared action plan guided by a long-term vision. The state governments of the Northeast, the federal government, eight commuter rail agencies, and Amtrak worked together through the NEC Commission to develop a detailed and efficient sequencing of infrastructure investment covering 150 projects along the corridor.
(complete documents here: http://nec-commission.com/connect-nec-2035/#download)

Each document (grouping states & segments along the NEC) is worth reading in its own right:
 
Last edited:

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,055
Reaction score
1,343

Jahvon09

Senior Member
Joined
Oct 2, 2011
Messages
1,993
Reaction score
171
Well, good to know that there's a 15-year plan to modernize the NEC. Kind of sucks that it will take that long to do it. :(
 