F-Line -- what about the newly extended Platform segments [most obvious due to the Ceiling structure at Park] to accomodate more cars in the train
I'm assuming that there must have been some relocating of utility lines, etc. to make way for the digging that went on at the stations in the old Cambridge-Dorchester Tunnel
That was part of the 1987-88 renovations for 6-car trains at all stops Central-Andrew + the Ashmont Branch. But you'll notice that at majority of those subway stations the platform extensions are much narrower. That traces out the structural limits of the station.
Utility relocation was probably only a minor thing for those renos because they were direct-attached to the existing stations with all their utility conduits. The construction profile wasn't big enough to engage much else.