TheRatmeister
Senior Member
- Joined
- Sep 23, 2023
- Messages
- 1,539
- Reaction score
- 3,093
This is indeed mentioned as a possibility in the presentation.I think you could, however, shift BU East to the other side of Granby Street, then eliminate Blanford.
This is indeed mentioned as a possibility in the presentation.I think you could, however, shift BU East to the other side of Granby Street, then eliminate Blanford.
They won’t be at the Type 10 spec until all Type 7s and 8s are gone from the system - since their doors open out they don’t allow level-boarding height platforms, the interim condition is 8” platforms like the rest of the current accessible green line stations (so bridge plates from the train will work), designed (like all other recent upgrades) to be relatively easy to convert to true level boarding when the time comes.One would hope that the T would create these new level boarding platforms to the Type-10 Spec, or at least plan it to be easily expanded in the near future... right?
I think you meant Type 7's and 8's. The Type 9's have the same plug doors the Type 10's will have and should have no problems with the raised platforms.They won’t be at the Type 10 spec until all Type 8s and 9s are gone from the system - since their doors open out they don’t allow level-boarding height platforms, the interim condition is 8” platforms like the rest of the current accessible green line stations (so bridge plates from the train will work), designed (like all other recent upgrades) to be relatively easy to convert to true level boarding when the time comes.
I think the Type 10s will be slightly taller IIRC.I think you meant Type 7's and 8's. The Type 9's have the same plug doors the Type 10's will have and should have no problems with the raised platforms.
I bet the social media person typed West Medford first, then didn't hit backspace enough
Those Orange Line riders had been advised to either use shuttle buses between Wellington and North Station, or use the Green Line between North Station and Copley — which was not an option during the service suspension caused by the pantograph problem.
The agency also is eyeing future transit-oriented developments at JFK-UMass station in Dorchester, Andrew station in South Boston and the Anderson Regional Transportation Center in Woburn.
"We have a garage that is in very, very poor condition and the decision has been made that it should come down"Maybe there's another thread for this, but the MBTA is more vocally/officially discussing an Alewife TOD RFP in the coming weeks.
It's a shame this wasn't a few years earlier, they'd probably have developers piling on their door steps to put some labs up.
The article quotes the director saying they're being realistic about housing not being as lucrative, and this project has some pretty large sunk costs already...OTOH once financing eases maybe we'll get some housing there. Although that will probably depend on the state and/or city being willing to assist with demo costs.
Nothing faster. Franklin is pretty delay-prone, especially on the segment shared with Foxboro trains (the original F'boro trial was pretty much a disaster for overall Franklin OTP). So the DT segments bring its schedule reliability up a lot, and may allow the T to strip out some excess padding in the schedules. All 3 phases will allow for true clockfacing schedules both for Forge Park and Foxboro. There's nothing more they'd need to do for Regional Rail except take care of the somewhat woeful state of station accessibility on the line.Random question, but, anyone come across a more up to date status of the Franklin Line Double Tracking project? From what I can tell, Phase 2 is still underway. It was supposed to be done in 2020, put on pause, and funding restored beginning of 2022, with the last communication being Poftak putting out a letter saying it's still underway which doesn't instill confidence. Phase 3 was supposed to be design complete in 2020 with the completion of Phase 2. The MBTA's project page is woefully out of date with Phase 2 being projected for a 2020 completion still.
Also, with the Phase 2 completion, the MBTA projected it will allow 35 vs 45 minute headways. Will Phase 3 and essentially fully double tracking the line allow 15 or 20 minutes headways or better? Will any of this allow faster travel on the line? It is ~30 mi and currently looks to take about an hour and 5 minutes or an hour and 13 minutes (guessing this is NEC vs Fairmont line routing), which seems pretty meh to average 30 mph.
The Google Earth Imagery from 4/25/23 is identical to 2021, but it looks like they got most of the work done back then - it appears they only have ~1.5 miles of track to put in. It is still programmed in the CIP, but the T has Keolis doing quite a bit of stuff these days.Random question, but, anyone come across a more up to date status of the Franklin Line Double Tracking project? From what I can tell, Phase 2 is still underway. It was supposed to be done in 2020, put on pause, and funding restored beginning of 2022, with the last communication being Poftak putting out a letter saying it's still underway which doesn't instill confidence. Phase 3 was supposed to be design complete in 2020 with the completion of Phase 2. The MBTA's project page is woefully out of date with Phase 2 being projected for a 2020 completion still.
Also, with the Phase 2 completion, the MBTA projected it will allow 35 vs 45 minute headways. Will Phase 3 and essentially fully double tracking the line allow 15 or 20 minutes headways or better? Will any of this allow faster travel on the line? It is ~30 mi and currently looks to take about an hour and 5 minutes or an hour and 13 minutes (guessing this is NEC vs Fairmont line routing), which seems pretty meh to average 30 mph.
There've been multiple ballast trains staged over the last month, so work has ramped back up bigtime this Spring.The Google Earth Imagery from 4/25/23 is identical to 2021, but it looks like they got most of the work done back then - it appears they only have ~1.5 miles of track to put in. It is still programmed in the CIP, but the T has Keolis doing quite a bit of stuff these days.
Random question, but, anyone come across a more up to date status of the Franklin Line Double Tracking project? From what I can tell, Phase 2 is still underway. It was supposed to be done in 2020, put on pause, and funding restored beginning of 2022, with the last communication being Poftak putting out a letter saying it's still underway which doesn't instill confidence. Phase 3 was supposed to be design complete in 2020 with the completion of Phase 2. The MBTA's project page is woefully out of date with Phase 2 being projected for a 2020 completion still.
Also, with the Phase 2 completion, the MBTA projected it will allow 35 vs 45 minute headways. Will Phase 3 and essentially fully double tracking the line allow 15 or 20 minutes headways or better? Will any of this allow faster travel on the line? It is ~30 mi and currently looks to take about an hour and 5 minutes or an hour and 13 minutes (guessing this is NEC vs Fairmont line routing), which seems pretty meh to average 30 mph.
Good Morning,
Thank you for your inquiry regarding the status of the Franklin Line Double Track Project.
Thank you for your follow-up inquiry. We wanted to update you on the progress of the Franklin Line Double Track Project, which is approximately 60% complete. As previously mentioned, the project has been put on hold since March 20, 2021.
The first phase of the project, covering about 4 miles of tracks between Walpole West and Rockwood Road near Norfolk Station, is currently 85% complete. The second phase, involving 3.5 miles of track from Norfolk Station to near Franklin Station, is 55% complete.
Once the project resumes, Keolis estimates that it will require approximately six months to complete all civil and track work. However, mandatory testing and commissioning of the new signal system will add further time.
Although the construction work is currently suspended, the construction permits are not in jeopardy. You may still see vehicles in the right of way performing normal railroad-related operations and maintenance activities.
Please be assured that the Norfolk Conservation Commission is aware of the construction delay and that all environmental control measures have been maintained."
Again, thank you for reaching out to us so we could provide this information.
Sincerely,
Keolis Customer Service
Good Evening,
We are in receipt of your submission regarding Franklin Line service.
The Franklin double track project began in 2019 but was put on hold in March 2021. However, in August 2023, the resumption of work began on this project. While we do not have a confirmed completion date available at this time, we will share more information with the public as it becomes available.
Thank you for reaching out to us.
Sincerely,
Keolis Customer Service