I don't think very many people would see that as better than the current method.
MBTA Continues to Successfully Advance Green Line Modernization Investments, Makes Significant Improvements in Green Line Reliability | News | MBTA
Official website of the MBTA -- schedules, maps, and fare information for Greater Boston's public transportation system, including subway, commuter rail, bus routes, and boat lines.
Over 20 miles of new signaling cable were routed through newly installed signal equipment during this most recent service outage, totaling 40 miles of cable installed so far – the MBTA plans to route 72 miles of new cable in total.
In the most recent shutdown the T only replaced and repaired 20 miles of signal cable out of 72. If all 72 miles of signal cable need replacing; why not just make the shutdown long enough to replace them all in a single shutdown instead of breaking it apart into several shutdowns? The T spends around 10-12 days just to replace and repair 20 miles of signal cable. To replace all 72 miles; the MBTA would need about 6 weeks total to do it all; so it could all be done in 6 weeks in one single 6 week shutdown.