Brookline High Stem Addition This appears to be progressing slowly, only the basement level foundation appears to be complete. I assume the site is very tight so the foundations and steel erection of the central portion needs to be completed first and they will work their way out to the perimeter foundations along Tappan St.
The latest construction timeline for the STEM Building is:
  • Site mobilization – (Completed July 2019)
  • Enabling – (Completed September 2019)
  • Demolition – Ongoing
  • Foundations – November 2019 to January 2020
  • Erection – January to April 2020
  • Facade – April to August 2020
  • Interiors – July 2020 to February 2021
  • Occupancy - February 2021
BHS Stem Addition First Flr.png
BHS Stem Addition Basement level.png



1.JPG
6.JPG


9.JPG
utility tunnel.JPG
13.JPG
 

dhawkins

New member
Joined
Jan 25, 2014
Messages
98
Reaction score
81
Same with BHS 9th Grade Bldg Cypress St, it looks like they are 4 to 6 month behind the schedule, foundations should be complete. I think it was such a mild winter and so many sites were hopping that they were probably fighting each other for concrete.

The construction timeline for the 111 Cypress Site is:
  • Site mobilization – (Completed July 2019)
  • Demolition –
  • Foundations – September 2019 to January 2020
  • Erection – January to May 2020
  • Façade – May to December 2020
  • Interiors – October 2020 to June 2021
  • Landscaping – April to June 2021
  • Occupancy - September 2021


BHS 9th Grade Bldg Cypress St.png