Highlights from the Huntington Ave Meeting:
- Median vs Side running has not yet been determined
- Transit lanes will be designed for trains and buses wherever possible
- Platforms will be 225ft to accomodate double type-10s.
- Design process to be largely completed by 2024
- Stated beginning of construction was set at 2027 though? Super unclear.
- Hyde Sq will not happen until after this project is complete, but the design will not preclude such an extension
- Stop consolidation is on the table, but will be weighed against the needs of local senior centers and the VA.
- Back of the Hill is almost certainly getting the axe, the grade is too steep for platforms.
- There is a type-10 mockup coming, it is currently in production
- Lots of concerns about the Huntington/South Huntington intersection
- Questions about TSP on the 66 going into Brookline
- Will outdoor dining at Brigham Circle be affected (A: The goal is no)
- One guy really annoyed at the Hilton using River Rd for dining
- Will the type 10s squeal?
- Some disbelief and skepticism that the type 10s will actually fit through Boylston
- Lots of other questions about the type 10s in general.