These slides have been posted on the MassDOT site. Seems like the Cambridge Street Bridge will be getting replaced starting next year.
If only there were alternate routes to get from Allston to Lower Alston during construction … Oh wait.These slides have been posted on the MassDOT site. Seems like the Cambridge Street Bridge will be getting replaced starting next year.
The bridge is NOT getting "replaced", it's getting repaired.If only there were alternate routes to get from Allston to Lower Alston during construction … Oh wait.
Still doesn’t change the fact that we funnel all the Allston Cambridge N-S traffic through 1 bridge. It’s a mistake that should have been fixed 40 years ago. This project needs more crossings.The bridge is NOT getting "replaced", it's getting repaired.
Still doesn’t change the fact that we funnel all the Allston Cambridge N-S traffic through 1 bridge. It’s a mistake that should have been fixed 40 years ago. This project needs more crossings.
The way our public feedback approach to design goes: a handful of Babcock bordering blue-hair boomer property owners would stop the whole project because they would suddenly be getting traffic on the streets we own. Malvern is all absentee landlord owned student slums = no power, no objections, no problem.Definitely agree. This is actually a problem that Boston as a whole has. Tons of roads going east-west to get downtown and back, almost no roads going north to south across the city. Trying to go from Dorchester across the city to Brookline, Allston, Brighton is a nightmare.
As far as here Babcock makes a lot more sense than Malvern which they plan to extend over, because Babcock goes all the way to Harvard st., Malvern just ends at Brighton ave. Maybe if there was a way for buses to turn from Commonwealth to Malvern it would work, but that would be a massive clusterfuck. They really need to extend both Malvern and Babcock. I would even say finding a way to extend Harry Agganis way would be good, because its pretty wide. Babcock is also muuch wider than Malvern. The more connections though the better.
The way our public feedback approach to design goes: a handful of Babcock bordering blue-hair boomer property owners would stop the whole project because they would suddenly be getting traffic on the streets we own. Malvern is all absentee landlord owned student slums = no power, no objections, no problem.
Build a bunch of bridges. Agganis, Babcock, Malvern, Pratt, Franklin. Build em all.
It's about more than buses, it's about tying the two neighborhoods togetherPerhaps I didn't follow the initial phases of the design closely enough, but were those actual objections raised that got us to our current design?
My impression is that Malvern is the only low-impact choice with current built environment for a bus connection. If you're not trenching the rail line significantly, you can't get the bridge grounded before Ashford St.
At Malvern, you buy out a single small moving/storage facility and you're all set.
At Babcock that would cut a moderately significant BU facility off from road access with no obvious way to create an alternate - and one that legitimately does need load-in/out capabilities by vehicle.
No opposition to additional ped/bike links (and there is the one planned at Babcock + the Franklin replacement), although I do think Pratt would be pretty low-value under the current plans.
-------
Ignoring the huge open question of what bus routes we're actually coming up with to use this bridge, I think you can solve if you want to send something inbound on Comm or south on Babcock pretty easily: Just use Babcock anyway - via Ashford. The Ashford/Malvern corner won't be a problem since you're taking the whole parcel anyway, Ashford/Babcock has the space to adjust the corner significantly. If there's delay at the light knock out the last 2 blocks of parking for a queue jump/bus lane from Gardner to Babcock - it's only about a dozen spaces.
It's about more than buses, it's about tying the two neighborhoods together
These slides have been posted on the MassDOT site. Seems like the Cambridge Street Bridge will be getting replaced starting next year.
I do not understand why they are keeping it as a two lanes eastbound at Harvard Ave when it is only ever fed by one lane from that intersection. It's such a waste of space in the most constrained part of the bridge!
I measured the distance and elevation change on Google Earth Pro, and the bridge approach would only be 3% to 5%, so it is geometrically doable, would fit within the exiting street footprint, and be compatible with the adjacent buildings. So, Babcock Street bridge it is!I think a Babcock St overpass over the RR tracks might be physically possible without the need to acquire any property. The ramp up to the new Babcock St bridge would start at the intersection with Gardner St, then climb up to be fully above Ashford St., which would cross under the elevated Babcock St at the existing grade, thus providing street access to the BU properties there. Then the elevated Babcock St would continue north over the tracks. I'll sketch it out later when I have time. It looks doable because Babcock St drops off a bit between Gardner and Ashford, and there are no driveways or garage entrances between those two points along Babcock St.
It's about more than buses, it's about tying the two neighborhoods togetherPerhaps I didn't follow the initial phases of the design closely enough, but were those actual objections raised that got us to our current design?
My impression is that Malvern is the only low-impact choice with current built environment for a bus connection. If you're not trenching the rail line significantly, you can't get the bridge grounded before Ashford St.
At Malvern, you buy out a single small moving/storage facility and you're all set.
At Babcock that would cut a moderately significant BU facility off from road access with no obvious way to create an alternate - and one that legitimately does need load-in/out capabilities by vehicle.
No opposition to additional ped/bike links (and there is the one planned at Babcock + the Franklin replacement), although I do think Pratt would be pretty low-value under the current plans.
-------
Ignoring the huge open question of what bus routes we're actually coming up with to use this bridge, I think you can solve if you want to send something inbound on Comm or south on Babcock pretty easily: Just use Babcock anyway - via Ashford. The Ashford/Malvern corner won't be a problem since you're taking the whole parcel anyway, Ashford/Babcock has the space to adjust the corner significantly. If there's delay at the light knock out the last 2 blocks of parking for a queue jump/bus lane from Gardner to Babcock - it's only about a dozen spaces.
I measured the distance and elevation change on Google Earth Pro, and the bridge approach would only be 3% to 5%, so it is geometrically doable, would fit within the exiting street footprint, and be compatible with the adjacent buildings. So, Babcock Street bridge it is!
As much as parties say they want to deck over the highway, I haven't seen anything suggesting it will actually happen. That's not in any of the plans that I know of, and no one has said they'll put up the money. Decking over the highway would be expensive now, and even more expensive after the project is done. When Harvard or MassDOT says it will be "possible" to deck over the highway later, that seems like some free BS they can throw in to make the project sound better.So, I'm under the impression that Harvard wants to deck over the highway and the tracks, creating a new "ground" floor comparable with the BU side.
I measured the distance and elevation change on Google Earth Pro, and the bridge approach would only be 3% to 5%, so it is geometrically doable, would fit within the exiting street footprint, and be compatible with the adjacent buildings. So, Babcock Street bridge it is!
What buses will be using this entryway? Are we talking about rerouting the 66? If there's a new bus line, I could see one originating from Kenmore and travelling down Comm ave to Lower Allston. I would think the Malvern crossing would be sufficient for that. I don't see West Station being a huge bus transfer if that's what the thought process is.With both babcock and malvern able to handle buses it could allow a better flow where they go up babcock, stop at the station, and come down malvern, vs having to do some type of loop around at the station. Plus then you would only have buses going in 1 direction on each street vs having buses coming both ways on the extremely skinny malvern street.
It's too much of a time chew to loop the 66/T66 and 64 there the way the proposed street grid is laid out. Chances are that's not going to happen...especially not with the proposed T66 because of the time sensitivity of its load-bearing route.What buses will be using this entryway? Are we talking about rerouting the 66? If there's a new bus line, I could see one originating from Kenmore and travelling down Comm ave to Lower Allston. I would think the Malvern crossing would be sufficient for that. I don't see West Station being a huge bus transfer if that's what the thought process is.
I think at the end of the day you're looking at just campus shuttle buses there, which doesn't require much bus infrastructure. Malvern's indeed probably sufficient for that lone BU shuttle bus, if BU even bothers to run a shuttle bus to what's going to be an all-Harvard property. What we'll have to see is whether the gigantic busways in the West render get VE'd down, because right now there's a LARGE discrepancy between projected bus capacity (too much by a lot) and projected bus utilization (or lackthereof).