By Adam Leech
aleech@seacoastonline.com
April 26, 2009 6:00 AM
PORTSMOUTH ? It will be a busy construction season on city streets as roadway projects and new buildings, both public and private, will begin or restart throughout the summer.
Portwalk
The most visible project will be the demolition of the Parade Office Mall, along Maplewood Avenue ? between Hanover and Deer streets, and construction of the first phase of Cathartes Private Investment's Portwalk development. Passersby will see fences go up around the site in the coming weeks with interior demolition expected to begin in May and be complete by mid-summer.
When the first phase of the project is complete ? expected to be spring 2010 ? there will be a five-story, 128-room Residence Inn by Marriott extended-stay hotel and approximately 12,000 square feet of retail space. There also will be a lot of open space where phases two and three will be built, at some future date.
Martingale
Those who drive down Bow Street on a regular basis have come to know intimately the mixed-use development at 99 Bow St., which will eventually fill the space between the Martingale building and its neighbors on both sides. The project includes retail, restaurants on the first level and office space on the upper levels of the six-story additions.
RRJ Properties had hoped to open the building this summer, but there were several delays. Construction was scheduled to restart this month. Developer Butch Ricci said he hopes the building will be "weather-tight" by the winter so interior work can be completed and the building open in summer 2010.
State Street
Steve Kelm's project at 68 State St., next to The Rosa Restaurant, is well under way and is expected to be done by the end of the year, according to Kelm. The project will be 11 residential condominiums that will include two retail spaces on the ground floor.
Only one small section of Pier II, at 10 State St., now remains. After more than four years of delays, demolition began on the building last week and will continue throughout the spring, followed by construction of the docks and foundation work, according to Lisa DeStefano, of DeStefano Architects.
Work will stop during the summer months to allow the Prescott Park activities to go on without interruption. In the fall, the shell of the building is expected to be completed. Interior work will take place in the months following and landscaping should be finished in the spring 2010.
Islington Street
The redevelopment of Kline's Furniture, at 51 Islington St., is still in front of the Planning Board, but could begin by the end of the summer, according to Kelm. The project will proceed in at least two phases and will not disrupt any traffic on the heavily congested corridor.
The current plan calls for two separate buildings, 3? and 4? stories tall, in place of the 2? story furniture store. The building along Islington would include retail space on the ground level with residential space above. The building facing Tanner Street would include only residential condominiums and would be built first.
The application of RKDOLLA, for 198 Islington St., received board approval last week to convert three apartments and a hair salon into 14 condominium units. It is not clear when the project will begin.
Developers for two of the larger pending projects in the city ? the redevelopment of the Meadowbrook Inn and the Westin Hotel, conference center and parking garage ? could not be reached. The city planning department has not been informed of work beginning at either site.
City and state projects
With the help of federal stimulus funds, the area of State Street ? from Pleasant Street to the Memorial Bridge ? will be completely rebuilt, much like the recent upgrades to Congress Street. The $2.2 million project will disrupt downtown traffic and parking lanes, but Public Works Director Steve Parkinson said the street will remain open. The project is not out to bid yet, but is expected to begin in July. It will take nine months to finish.
Also receiving stimulus funds, the $23 million replacement of the city's water treatment plant in Madbury will begin construction this summer. The new plant will be built next to the 51-year-old existing plant and take approximately two years to complete.
The state's $7.5 million Route 33 project to replace the B&M Railroad Bridge will not be complete until fall 2010. The project includes traffic signals at Griffin Road and Islington Street, upgrades to the traffic signal and roadway at Peverly Hill Road, closing off Plains Avenue at Peverly Hill Road, as well as other roadway, sidewalk and traffic calming improvements.
The $4 million sewer project at Bartlett Street and Islington Street will involve some disruption to traffic because they will have to cross Islington to make the new connection, but Parkinson said the road will remain open. The project is not out to bid yet, but is expected to start this summer and take approximately one year to complete.
Some time in September, the city will begin construction of a small waterfront park on Ceres Street where the decks for Poco Bow Street Cantina are. The decks will be rebuilt closer to the building, while the city creates the park. Among the other improvements are drainage, paving, lighting and sidewalks. The $800,000 project may be done by the winter, but could require further work in the spring.
The Woodbury Avenue improvements started last year are expected to finish in June, according to Parkinson. The remaining work on the $1.2 million project is mostly limited to paving.
Phase II of the Raleigh Way streetscape project, from Ranger Way to Saratoga Way, is expected to start in July and be complete by the fall. The $780,000 project consists of a new water line, sewer line and drain line, new granite curbing, trees, sidewalks and paving.
The $229,000 Market Street sidewalk project will start during the summer and will bridge a gap that currently exists between downtown sidewalks and the end at the Port Authority, to the sidewalks west of Michael Succi Drive.
The city will also spend $250,000 from the capital budget to replace sidewalks on Middle Street, from Union to Cass Street and Park Street Intersections. The project will start this summer and take approximately two months.
The 35-year-old pumping station for the Rye sewer line is in the process of getting an $800,000 upgrade and should be completed this year.
The reconstruction of Gates, Hancock and Howard streets and a portion of Washington Street will include an upgrade of sewer and water lines in the area. The $678,000 project is expected to be done by early summer.
Bike lanes will be painted on city streets in the Elwyn Park area this summer as well.
The following streets are also scheduled for paving this summer: Central Avenue and Myrtle Avenue; McGee Drive; Shaw Road; Willard Avenue and Marston Avenue; Oak Street, Orange Street, Mangrove Street, Birch Street and Kearsarge, from Birch to the railroad bridge; Market Street from Deer Street to the railroad tracks; and Maplewood Avenue from the Bypass Bridge to Dennett Street.
Funding for many city roadway projects is provided by state or federal grants.