Will be a case study in structural engineering with the columns and cantilever beams required to hold this thing up, and the constraints of keeping a busy train station open the entire time right underneath. I really hope this thing starts "going up" next month..
Stefal -- call everyone's attention to the BIG Document NPC*1 filed with the BDPA just a bit before the final approval
NOTE the following [3-4 Development Review Component or 124/220]:
The foundations for the Phase I Tower are planned to consist of high capacity reinforced concrete Load Bearing Elements (LBEs) bearing in bedrock and installed using slurry wall construction techniques.
[3-5 Development Review Component Epsilon Associates, Inc. or 125/220]
The Proponent, in collaboration with the MBTA and other parties impacted by construction, has prepared a phased construction management plan for construction activities within the transportation center (MBTA CMP) with the goal of minimizing or mitigating impacts upon passenger use of South Station throughout construction, especially upon the passenger waiting area in the Head House concourse.
The
MBTA CMP includes detailed drawings depicting each phase of construction, and outlines mitigation measures to ensure adequate passenger circulation and continued access to the waiting area and concourse facilities. Under the current design, changes to the existing Head House concourse space are limited to the construction period.
At no time will the current design result in the reduction of square footage within the concourse. Throughout the approximately four year period of construction, all existing access points to the Head House and Head House concourse via Dewey Square, Summer Street, and Atlantic Avenue will remain open.
Similarly, pedestrian access from the train platforms to the adjacent U.S. Post Office facility and Dorchester Avenue will continue. The MBTA CMP describes how continuous access from the Head House to the bus terminal can be provided during construction.
In particular:
Figure 1-3 Project Axonometric (Looking East) – Current Project
Figure 1-4 Project Axonometric (Looking West) – Current Project
page 14/220
11397/South Station Air Rights/NPC 1-5 General Information / Project Description Epsilon Associates, Inc.
1.3.2 Currently Proposed Project
The Project will be similar to the previously approved project, as it will continue to include three buildings with a mix of residential, office, retail, and/or hotel space. 2 The Project continues to include three phases, of which only Phases 1 and 2 are changing.
Phase 3 will continue to be the same as proposed in the Final PIR. 3
A list of changes to the Project is included in Section 1.3.3.
- Figure 1-2 includes an axonometric plan showing the previously approved project, and
- Figures 1-3 and 1-4 show axonometric plans showing the currently proposed Project.
- Figure 1-5 Rendering of Phase 1 from the North
- Figure 1-6 Area to be Added to the Planned Development Area [about 3,000 sq ft to the original 358,000 sq. ft]
- Figure 1-8 Phase 1 Sections – Current Project
- Figure 1-10 Project Section – Current Project
- Figure 1-12 Project Plan at Sky Street – Current Project [this is the level where all the magic happens as the tower suddenly sprouts]
- Figure 1-16 Project Plan at Grade – Current Project [level how you get to the level where the magic happens -- this is where Atlas holds up the tower]
- Figure 1-17 Project Plan at Phase 1 Residential Sky Lobby and Phase 2 Amenity Level – Current Project [only really of interest if you buy a condo or have a friend who does -- unless you can convince them to give you an approval tour]
- Figure 2-1 Site Location Map -- [puts it all into context]
- Table 2-4 MBTA South Station Commuter Rail Service and Capacity [fascinating -- all of the CR lines into South Station have a lot of capacity which is under-utilized]
Tower (Phase 1)
A, 43-story4 tower approximately 640-feet to the top of the highest occupiable floor, will include office space on the lower floors and residential units (rental or condominium) on the upper floors—approximately 711,000 sf of office use including amenity, retail, and conference facilities on floors 1 to 26, and approximately 321,000 sf of residential space containing approximately 175 residential units on floors 28 to 43. Although the height to the top of the architectural enclosure of the rooftop mechanical equipment has not changed, the zoning height has changed since zoning height under the Development Plan is measured to the top of the highest occupiable floor. The change in use from all office to mixed-use office and residential, as well as a change in structural design, has allowed for the addition of two floors to the building without increasing the overall height of the building. The office and residential ground floor entrance lobbies will be located on Atlantic Avenue. From the lobby area, office tenants and visitors will use an elevator to access the Sky Street level which will include connections to the elevators for the office portion of the tower, restaurant and accessory retail/amenity space, the parking garage, and the Phases 2 and 3 lobbies. Residents will take elevators from the Atlantic Avenue lobby to an upper level residential lobby with connections to gardens and terraces on the roof of the expanded parking garage, and to the elevators serving the residential condominiums. Mechanical levels will be below the office Sky Lobby level and between the top tower office floor and the bottom tower residential floor. Figure 1-5 shows a rendering of Phase 1.
1.8 Schedule [page 1-30 or 40/220] [obviously the dates have to be shifted about 3 years]
The redevelopment of the site will proceed generally from the north end of the site to the south end. The Project phases may be constructed during different periods of time. The Proponent currently estimates that construction of the bus terminal expansion, the ancillary transportation improvements, the next phase of the parking garage and the Phase 1 building will commence in 2017, and will be completed approximately four years after commencement of construction.
Construction of the Phase 2 building is expected to commence within one year after completion of the Phase 1 building, and will be completed approximately two years after commencement of construction.
Construction of the Phase 3 building is expected to commence within one year after completion of the Phase 2 building, and will be completed approximately two years after commencement of construction. However, the schedule may be expedited or extended depending on market forces.
3.1.7 Geotechnical/Groundwater
The foundation design will be very similar to that described in the Final PIR. Installation of the Phase 1 building foundations is not anticipated to cause adverse impacts to the existing South Station structure nor to neighboring facilities or groundwater levels.
The Phase 2 and 3 buildings will be supported on existing foundations, and also not cause adverse impacts.
The foundations for the Phase I Tower are planned to consist of high capacity reinforced concrete Load Bearing Elements (LBEs) bearing in bedrock and installed using slurry wall construction techniques. The use of slurry wall-type excavation methods for foundation installation, common in Boston, results in very low vibrations and noise, avoids loss of ground and ground movements, and is very protective of nearby buildings and other facilities.
The LBEs will also not transfer vertical or horizontal loads to adjacent structures. A reinforced concrete LBE “cap” will be constructed on top of the LBE units within an excavation supported laterally by drilled-in soldier piles with lagging or drilled-in secant piles.
Two columns supporting a portion of the existing train station concourse curtain wall and roof are immediately adjacent to the planned LBE foundation of the Phase 1 building. As a conservative precaution these columns, currently supported on end-bearing piles, will be underpinned using drilled-in micropiles installed deep into bedrock in advance of LBE installations.
*1
SOUTH STATION AIR RIGHTS
NOTICE OF PROJECT CHANGE
Submitted to: Boston Redevelopment Authority
One City Hall Square Boston, MA 02201
Submitted by: South Station Phase I Owner LLC
c/o Hines Interests Limited Partnership
One International Place, 11th Floor Boston, MA 02110
Prepared by: Epsilon Associates, Inc. 3 Clock Tower Place, Suite 250 Maynard, MA 01754 In Association with:
Pelli Clarke Pelli Architects
Kendall/Heaton Associates, Inc.
Goulston & Storrs
Vanasse & Associates, Inc.
Howard Stein Hudson
Noresco
July 29, 2016