Amtrak representatives to hold two community meetings on bridge replacement projects over Bush and Gunpowder rivers
I feel like the Bush, Gunpowder, and Susquehanna bridge replacement projects have gone a bit under the radar. Once the bridges are replaced, the Acela will be able to go 160 MPH for part of the trip in Maryland. There has also been talk about future speed improvements in Delaware to allow for 160 MPH (the current limit is 135 MPH). These speed increases will significantly improve the Acela's performance between Philadelphia and Washington.Amtrak representatives will meet with community members and local waterway users on Aug. 18 in Joppatowne to present updates and address public concerns regarding upcoming replacement projects for two rail bridges over the Bush and Gunpowder rivers.
[...]
The projects involve replacing existing aging drawbridges with fixed structures designed to accommodate higher train speeds along Amtrak’s Northeast Corridor. Under current plans, the Bush River Bridge will be replaced with a fixed bridge featuring a 30-foot vertical clearance above mean high tide to support train speeds up to 160 mph. The Gunpowder River Bridge will be replaced with a fixed structure offering 15 feet of vertical clearance above mean high tide to support speeds of 145 mph or higher. Horizontal clearances for both channels are slated to remain unchanged.
Also, construction began last week on the TIME-1 project in Connecticut, which will increase the speed limit from 70 MPH to 90 MPH on a three-mile stretch of track in Bridgeport and Stratford:
Connecticut begins project to shave 25 minutes off Metro-North by 2035
Governor Ned Lamont SOM ’80 and state transportation officials broke ground Monday on a $1.6 billion effort to modernize the Metro-North Railroad’s New Haven Line, the busiest commuter rail service in the country.
The initiative, known as TIME-1, is the biggest component of TIME FOR CT, a major capital investment program that Lamont introduced in 2021 to improve Connecticut’s rail infrastructure. Once all three phases of TIME-1 are complete in 2035, state officials say, passengers traveling between New Haven and New York City will save about 25 minutes on a trip that typically takes two hours.
[...]
As part of the first phase, the state’s transportation agency is modernizing track and signal infrastructure, as well as installing new overhead wires and structures that power trains. The upgrades will let Metro-North trains reach 90 miles per hour in parts of the corridor where the current maximum speed is only 70 miles per hour.
The future of the Northeast Corridor is looking good. There are a lot of projects planned or under construction that will increase speeds and improve reliability:
Project Name | Location | Speed Increase | Estimated Completion Date | Project Status |
| Portal North Bridge | Kearny & Secaucus, NJ | 60 MPH to 90 MPH | 2026 | Mostly complete, second track to be connected by November |
| East River Tunnels rehabilitation project | New York City | No speed increase | 2027 | Under construction |
| Dock Bridge rehabilitation project | Newark & Harrison, NJ | No speed increase | 2028 | Under construction |
| TIME-1 speed improvement project | Bridgeport to Stratford, CT | 70 MPH to 90 MPH | 2029 | Under construction, broke ground on 8/3/26 |
| Walk Bridge replacement project | Norwalk, CT | 30 MPH to 45 MPH | 2030 | Under construction |
| Connecticut River Bridge replacement project | Old Saybrook & Old Lyme, CT | 45 MPH to 70 MPH | 2031 | Under construction |
| Saugatuck River Bridge replacement project | Westport, CT | 45 MPH to 90 MPH | 2033 | Groundbreaking planned for 2030 |
| Pelham Bay Bridge replacement project | New York City | 45 MPH to 70 MPH | 2034 | Groundbreaking planned for 2029 |
| Bush River Bridge replacement project | Perryman, MD | 125 MPH to 160 MPH | 2034 | Groundbreaking planned for 2028 |
| Sawtooth Bridges replacement project | Kearny, NJ | 60 MPH to 90 MPH | 2035 | Under construction |
| Gunpowder River Bridge replacement project | Chase, MD | 125 MPH to 145 MPH (or higher) | 2036 | Groundbreaking planned for 2028 |
| Frederick Douglass Tunnel (B&P Tunnel replacement) | Baltimore, MD | 30 MPH to 110 MPH | 2036 | Under construction |
| Devon Bridge replacement project | Milford, CT | 40 MPH to 70 MPH | 2036 | Groundbreaking planned for 2030 |
| Susquehanna River Bridge replacement project | Perryville & Havre de Grace, MD | 90 MPH to 160 MPH (south bridge) & 125 MPH (north bridge) | 2036 | Groundbreaking was planned for 2025 but did not occur |
| Gateway Program | New York City & Jersey City, NJ | Capacity increase, no speed increase | 2035 (new tunnel), 2038 (rehabilitation of old tunnels) | Under construction |
The Northeast Corridor will be in much better shape by the end of the 2030s, but there's still a lot left to be desired. The Cos Cob bridge replacement project is planned but unfunded, with no estimates for groundbreaking or completion. I don't think design work has even started for that one. The Shell Interlocking grade separation project in New Rochelle is badly needed, but it's not currently planned or funded. Grade-separating some of the crossings in Connecticut (especially the Miner Lane crossing) is also badly needed, but I'm not aware of any serious or funded plans to eliminate them. I'm also not sure if crossing eliminations in CT will allow for further speed increases or not. The Readville-to-Canton third-track project is also important, but I'm not sure if there's any funding allocated for it. I haven't been able to find anything about when it will break ground or be completed. Restoring the fourth track through Milford, CT is also very important, but it still lacks funding for design and construction. Additionally, Amtrak needs to finish the constant-tension catenary project in New Jersey, so that the Acela can travel at 160 MPH instead of 135 MPH. They finished installing the constant-tension catenary between New Brunswick and Princeton Junction in 2022, but AFAIK there's been no further catenary work done between Princeton Junction and Trenton. Once the second half of the project is completed, the stretch of track between New Brunswick and Trenton will be the longest continuous stretch of 160 MPH track on the entire Northeast Corridor.