Latest public update on progress from Consigli/Greystar:

Recently Completed Activities: The earthwork subcontractor completed site soil excavation for the foundation and soil haul-off. Waterproofing of the basement slab is complete with structural rebar and MEP slab installation taking place over the next week. The future crane base has also been placed.
Upcoming Activities: In the coming week the concrete subcontractor will place the 5’ structural slab for the building foundation. This will represent a milestone for the project and be followed by the start of vertical construction of the foundation walls and core wall structures in the basement level.
 
Last edited:
This project is moving at lightning pace compared to the other small tower project on La Grange.

I hope we still get the Motormart Tower... though feeling doubtful about that right now.
 
Waterproofing starts Thursday. Crane going up this weekend. Formwork starts Monday. Lagrange has a caisson foundation system due to poor ground conditions.
inherently slower than a Mat on virgin ground.
 