Green Line Extension to Medford & Union Sq

Looks like they’re getting the Pearl St substation online…

9021ECD6-D83F-40D3-B90D-593FC65A3BE0.jpeg
 
What’s the plan for stabilizing the hill between Gilman station and the Somerville buildings (hilltop)? Is it part of GLX or the city’s project?

Right now it is a crazy jumble of retaining wall, gravel, and dirt.
 
Another sign of GLX progress is that the speed restriction on the Lowell Line has been nonexistent on both morning inbound evening outbound trips through GLX the past two days.
 
The T only says “in the next few weeks” now. They have recently made a bunch of progress with the duct banks on both sides of the bridge, after months of leaving open trenches.
 
Last edited:
The T only says “in the next few weeks” now. They have recently made a bunch of progress with the duct banks on both sides of the bridge, after months of leaving open trenches.

Any word on the adjacent medford street bridge? There was talk about maybe leaving that closed permanently and it being a home for a farmers market and other seasonal stuff. Is that the final plan?
 
There is a whole Gilman Square SomerVision process, that is separate from the GLX. I think the GLX contractors are working to reopen the bridge in “the next few weeks.”
 