Revere breaks ground on largest public school project in Massachusetts
REVERE, Mass. —
Revere has begun construction on its new high school, the largest public school project in Massachusetts, located on the former Wonderland Greyhound Park site.
....
The new building will hold more than 2,400 students, an effort to relieve citywide overcrowding. It will also be environmentally state-of-the-art, featuring geothermal heating and cooling, a micro-forest and 12.8 acres of public open space.
"We're in the middle of wetlands and we want to make sure that we replicate that and we bring the wildlife back to the area," Keefe said.
The project will cost about $493 million, with the Massachusetts School Building Authority helping to support almost half of that cost.
....
Construction will begin immediately, and the project is on track to be completed in three years.
https://www.wcvb.com/article/revere...blic-school-project-in-massachusetts/65780813
----
Happened to spy this one while out by Wonderland this evening...and yes they've mobilized on site: