I agree, but Parcel G was complicated by the realignment of Northern Ave. It used to cut through Parcel G and now it frames parcel G. But some of the utilities still run though Parcel G. Not insurmountable but it takes time to relocate them.
I think the last one is the one being relocated right now (you can see current construction in front of Ocean Prime and the courthouse). Eversource owns two 115kV circuits that are being relocated. Both are pipe type cables. That means each circuit consists of three conductors inside an 8" steel pipe that is filled with pressurized oil to insulate and cool the conductors. So the process of replacing it is time consuming:
- Cast new splice vaults where the new pipe will meet the existing pipe.
- Install new pipe. For these two circuits it was something like 800' each circuit.
- Wait for an outage window (those are critical circuits so only one can be de-energized at a time and it needs to occur in either fall or spring - not during peak loads).
- Install 2 freeze pits once outage begins. Freeze pits uses super-cooled nitrogen to freeze the oil "upstream" (i.e., on the substation side) from where your cutting into the existing pipe. So you only lose the oil between the two freeze pits and not all the oil back to the substations/terminations.
- Drain oil and remove section of conductors.
- Pull in new conductors and splice to existing conductors at the manholes.
- Re-energize line.
- Wait for next outage window so you can repeat steps 4 through 7 on the second circuit. The good news is I think Eversource is planning to get both outages done this fall. I don't think they need to wait for the spring for the second outage.
TL/DR - Eversource needs to finish relocating 2 underground transmission lines before work can start on Parcel G.