Hey All-
It's time for another update. One of the final updates for this project, as anticipated opening is 4/1/18.
This is a rather small update, as there's not much to show, except work at Bellingham Square Station. Most of the other stations are just about done, with just very minor updates being done (road/sidewalk striping, station signs, system maps, etc). The only noted exception is there's still a railroad gate in the middle of Spruce street that needs to be moved. But the new gate is installed so maybe it's just a matter of time.
As said above, Bellingham Square station is lagging behind. The ramp is still not done, and didn't look like much work was done between the last set and this one. I was told months ago that the panels for the system were on order and would take a bit. The rest of the station is almost done, looks like its just finishing up lighting & signage.
They still have roughly 45 days until opening so it may just be done under the wire.
I also was told that the T has been running a few buses on the bus way to 'test it out' so we're very close to being done!
If you'd like to see the previous photo sets they can be found here by clicking on the links below:
Pics from 4/25/15
Pics from 6/20/15
Pics from 8/1/15
Pics from 9/19/15
Pics from 10/31/15
Pics from 1/9/16
Pics from 3/12/16
Pics from 4/16/16
Pics from 5/15/16
Pics from 6/26/16
Pics from 8/13/16
Pics from 10/5/16
Pics from 11/10/16
Pics from 12/14/16
Pics from 2/2/17
Pics from 3/23/17
Pics from 4/20/17
Pics from 6/3/17
Pics from 7/22/17
Pics from 9/9/17
Pics from 12/16/17
And if you'd like to see the ALL of NEW photos, you can click
here
And now for the highlights. I am going to severely abbreviate this because there's just not much to see and restrict this to area's where there is construction progress. If you'd like to see the whole set, you can click on the link above.
----
Signage is up at Box District Station
----
Bellingham Square Station as seen from the Washington Ave bridge
----
Another view of Bellingham Square Station as seen from the Washington Ave bridge
----
Bellingham Square Station and the unfinished ramp system as seen from the Washington Ave Bridge. I am having a hard time conceptualizing this, it just seems too low. Unless the concrete is the pillars for the system.
----
Another view of the unfinished ramp system at Bellingham Square Station
----
Bellingham Square Station (outbound) as seen from Arlington @ Sixth.
----
Spruce Street and it's existing RR Crossing that needs to be moved still
----
So this picture has me a bit perplexed. I was told we would be getting signals at all crossings except for Cottage Street, which would be added later (it's a low volume intersection). But this one.. I have a call out to MassDOT (see below) about something else, so I will ask. The crossing lights at Everett Ave, Spruce, and Arlington Streets are crucial for this project to work well.
-----
So that's it for now. As I said. A small update. I sent out a request for a tour earlier this week, I was kind of hoping MassDOT would reply before the weekend so I would know to take pictures or not. So I did anyways.
However, I may have a tour in the next couple of weeks, so the next set could follow very soon after this one.
As far as an opening day set, thankfully it starts on a Sunday. I plan on photographing (and video recording) the first run, and a few other fun features.
But more to come.
As always, let me know what you think!