Equilibria
Senior Member
- Joined
- May 6, 2007
- Messages
- 7,002
- Reaction score
- 8,124
Compared to the project's history, this is moving at lightning speed...
So just found out MassDOT has a incentive/disincentive on the project.
The Kendrick Street Bridge, I-95 NB off Ramp and I-95 SB on Ramp must be opened to traffic by September 26th, 2016 and the contractor will receive $11,000 a day for every day the contractor finishes ahead of schedule up until August 20th, 2016. The contractor will also be fined $11,000 a day for every day later then September 26th, 2016. Total the contractor can receive a $407,000 bonus or the contractor will have to pay the same as a penalty for a late completion.
Substantial Completion of the entire project must be achieved by February 24th, 2019. The contractor can receive a $30,000 a day bonus for a early completion up until October 13th, 2018. The contractor will be fined $30,000 a day after February 24th, 2019 for a late completion. The contractor can receive a total of $4,020,000 bonus or will have to pay the same in a penalty for late completion.
Final Project completion is scheduled for April 25th, 2019.
Sheesh dude...Jeez...I just drove this stretch for the first time in 2 months, and they have accomplished absolute bupkis this summer. No progress on the new Highland Ave. overpass, no progress on the still un-graded median south of Kendrick that hasn't been touched since last November, little fussing-around progress at the new Kendrick interchange, no further sound wall assembly, nothing apparent at the Central Ave. bridge, Route 9 bridge only about 30% renewed, and the heaviest concentration of equipment is still fluffing the pillows at the rock cliff north of Central that they shaved back 4 months ago (despite it not being on the highway footprint in the first place).
This is starting to look like a repeat of the Dedham segment that ground to a near-halt for a full year. Isn't this Needham contractor on a tight time limit of this Fall for spending the fed stimulus contribution to this segment? 'Cause it looks like things are careening towards levying contract penalties at the rate they're not-going.
Jeez...I just drove this stretch for the first time in 2 months, and they have accomplished absolute bupkis this summer. No progress on the new Highland Ave. overpass, no progress on the still un-graded median south of Kendrick that hasn't been touched since last November, little fussing-around progress at the new Kendrick interchange, no further sound wall assembly, nothing apparent at the Central Ave. bridge, Route 9 bridge only about 30% renewed, and the heaviest concentration of equipment is still fluffing the pillows at the rock cliff north of Central that they shaved back 4 months ago (despite it not being on the highway footprint in the first place).
This is starting to look like a repeat of the Dedham segment that ground to a near-halt for a full year. Isn't this Needham contractor on a tight time limit of this Fall for spending the fed stimulus contribution to this segment? 'Cause it looks like things are careening towards levying contract penalties at the rate they're not-going.
I agree. The 95/93 interchange in Woburn is by far the worst in the state. I have to believe some temporary fixes are available before they make a flyover 10 years from ow. If anyone wants to experience it, try doing it during rush hour for a week and you'll grow to hate the Burlington/Woburn 128 area.
I agree. The 95/93 interchange in Woburn is by far the worst in the state. I have to believe some temporary fixes are available before they make a flyover 10 years from ow. If anyone wants to experience it, try doing it during rush hour for a week and you'll grow to hate the Burlington/Woburn 128 area.
The land drop on 128 just north of the interchange really really does not help things at all. Wouldn't be totally crazy to add a 4th lane on 128 from rt 28 up to the 95 split in Peabody (and then continue with an additional third lane on 128 from the Peabody split to 114).