Most of this site has been demolished.
R RandomWalk Senior Member Joined Feb 2, 2014 Messages 3,033 Reaction score 4,285 Dec 5, 2022 #81 Most of this site has been demolished.
R RandomWalk Senior Member Joined Feb 2, 2014 Messages 3,033 Reaction score 4,285 Aug 8, 2023 #82 This one has been moving the tents around the plot for months. Given the airlocks and ventilation, they must be doing some remediation inside. At least there is some progress on the actual construction.
This one has been moving the tents around the plot for months. Given the airlocks and ventilation, they must be doing some remediation inside. At least there is some progress on the actual construction.
R RandomWalk Senior Member Joined Feb 2, 2014 Messages 3,033 Reaction score 4,285 Nov 13, 2023 #83 From a week ago. The mechanicals are visible all the way to the Mass Ave/Alewife Brook Parkway intersection.
From a week ago. The mechanicals are visible all the way to the Mass Ave/Alewife Brook Parkway intersection.
S sm89 Senior Member Joined Apr 29, 2014 Messages 1,157 Reaction score 444 Feb 5, 2024 #85 Why are there so many huge white tents all over the site?
R RandomWalk Senior Member Joined Feb 2, 2014 Messages 3,033 Reaction score 4,285 Feb 5, 2024 #86 Abatement of the soil. Dewey & Almy wasn’t exactly gentle with the land.
Charlie_mta Senior Member Joined Jul 15, 2006 Messages 4,338 Reaction score 5,978 Feb 5, 2024 #87 RandomWalk said: Abatement of the soil. Dewey & Almy wasn’t exactly gentle with the land. Click to expand... Better living through chemistry, as they used to say.
RandomWalk said: Abatement of the soil. Dewey & Almy wasn’t exactly gentle with the land. Click to expand... Better living through chemistry, as they used to say.
V Vagabond Active Member Joined Mar 17, 2017 Messages 658 Reaction score 1,395 Apr 18, 2024 #89 The construction team publishes their monthly activity overview Alewife Park – Project Information and Construction Updates Attachments 1713463143226.png 1.3 MB · Views: 48
The construction team publishes their monthly activity overview Alewife Park – Project Information and Construction Updates
R RandomWalk Senior Member Joined Feb 2, 2014 Messages 3,033 Reaction score 4,285 Nov 3, 2024 #92 Pile driving for another structure. There is also a foundation completed further back.
Charlie_mta Senior Member Joined Jul 15, 2006 Messages 4,338 Reaction score 5,978 Nov 3, 2024 #93 sean99090900 said: View attachment 52955View attachment 52956 Click to expand... I used to go to Boy Scout meetings in the building it replaced when I was a kid. The new buildings are great.
sean99090900 said: View attachment 52955View attachment 52956 Click to expand... I used to go to Boy Scout meetings in the building it replaced when I was a kid. The new buildings are great.
N NHMaples New member Joined Feb 2, 2023 Messages 69 Reaction score 122 Nov 4, 2024 #94 How do they handle it if they hit ledge while driving that steel into the earth? I've watched well driving companies pound their way through, but that has a much smaller diameter than what's required here.
How do they handle it if they hit ledge while driving that steel into the earth? I've watched well driving companies pound their way through, but that has a much smaller diameter than what's required here.
R RandomWalk Senior Member Joined Feb 2, 2014 Messages 3,033 Reaction score 4,285 Nov 4, 2024 #95 They drive the pile until it hits “refusal” and trim off the excess. The piles have marks on the sides to document how deep they have been driven.
They drive the pile until it hits “refusal” and trim off the excess. The piles have marks on the sides to document how deep they have been driven.