F-Line to Dudley
Senior Member
- Joined
- Nov 2, 2010
- Messages
- 9,347
- Reaction score
- 9,600
Not really. For most out-in-the-open double-track OCS modern installations it's 1 pole overhanging both tracks, alternating sides of the ROW. Amtrak didn't significantly overbuild it when it did New Haven-Boston 25 years ago. There isn't a significant increase in catenary cost for double-track. And constant-tension catenary is a lot less visually intrusive with its structures than those giant old variable-tension towers you see across the New Haven Line and old Pennsy-instlall south-of-NYC NEC. You do need to have substations powered amply enough for 2 tracks, but they'd have to do that anyway for charging BEMU's saturating service on a DT corridor so ultimately the OCS is not bigly variable by track capacity.Given that they say "388 route miles, 650 track miles", I assume that they are counting each track as separate. Which I don't think is actually that disingenous -- wire cost is 1:1 per track mile (at least just in terms of the physical wire itelf), the catenary "poles" also increase in size and material if they cover multiple tracks, and the underlying electrical demand also increases with parallel tracks, since you can run that many more trains.
Caltrain electrification was a scandal it was so badly mismanaged. And you can't rely on that figure in a contextual vacuum because their whole "Modernization" project wadded up a lot of electrification-unrelated things into the project bucket, like grade crossing treatments and elimination and their disastrously scrapped custom PTC system. And they got absolutely fleeced on their vehicles because Stadler stuck Caltrain with all the financial risk for their invasive vehicle mods, and they took a complete bath on it (and still are, being on the hook for a bonkers $80M for a single 4-car BEMU demonstrator set for the Gilroy tail).I haven't checked your cost figures for Caltrain, but honestly that sounds like it's probably exactly how they came to their cost estimate (for better or worse). Particularly in a verbal presentation, and one where they are explaining why they are forgoing plans for systemwide electrification in the inital build, saying "$27B" would imply a higher level of precision than is actually accurate, so rounding to "$30B" is more accurate overall.
That all being said, yes, using Caltrain figures is debatable, and it seems like there is a lot of a priori thinking going on.
Did the NEC screech to a halt when Amtrak mass-erected 155 miles of cat supports over the course of 3-1/2 years? No. And they didn't impale themselves on environmental regs either despite much of the Shoreline in Connecticut being along waterfront estuaries and the straightaways in Massachusetts being heavily based on swamp embankments.I mean, I think there are pretty obvious drawbacks. It's not the overhead lines, it's the catenary poles every so many feet and the concrete used to hold them in place, and it's the disruption from construction, both in terms of the physical presence of equipment and in terms of the inevitable runoff.
This isn't a wild speculative question. Those 155 miles of NEC Shoreline were EIS'ed in the modern era. Caltrain was EIS'ed in the modern era. Denver FasTracks was EIS'ed in the modern era. Numerous LRT systems were EIS'ed through wetlands in the modern era. Hell, NJ Transit did some fresh electrification extensions on the North Jersey Coast Line as late as 1988. We have the datasets on how much environmental regs dinged up those projects. It's not an onerous burden. Yes, they'll have to site the off-ROW substations in places where the wetlands ain't. But there's a few linear miles of 'wobble' in where a sub can be sited and still power its designated 30-mile track section, so even that costly item does not incur onerous EIS'ing challenges. We've done this...recently...and extensively even in this country. It's not a "Thar be dragons!" unknown to concern-troll about, though I know that's exactly what they're doing here.Now, to be clear, I'm not saying it's a valid justification for not electrifying tracks through wetlands. Far from it: at this point, my heretical take is that we should radically de-emphasize EISs for mass transit projects. (Imagine debating whether to use water from a fire hose on particular corners of a burning house, since the water might damage priceless paintings inside. We must put out the fire, and so we must get people out of cars.)
But the potential impact on wetlands seems relatively easy to imagine; the answer isn't to deny that impact, but to acknowledge it and frame it against the harm of the no-build alternative.