Alright, so just modeling out what BEMU vs electrification costs would look like, and the formula I have right now for fast-charging at the terminals is [(Round trip time*TPH*BEMU cost delta)+(Total charging time*TPH*BEMU cost)]/Electrification cost+Charging station cost/Electrification Cost. This take into account the BEMU premium for X number of trains running on a line given a length of time and desired frequency, and the number of extra trains required given an amount of charging time. So, with the numbers I could find, which are for Germany so double everything for US numbers. (haha jk... unless?):
The one thing I'm aware of is station cost increases on short lines, where more than one train might need to be charging at once for example. That's very difficult to model so I'm probably just going to ignore it for now. Are there any other cost factors people think I should include?
- BEMU cost premium is around $3m
- Charging time at each end is around 20-30 minutes, I've estimated 45 minutes round trip.
- BEMU cost of around $7m
- Electrification cost of around $4m per mile
- Charging stations run around $8m per, so 16m total.
The one thing I'm aware of is station cost increases on short lines, where more than one train might need to be charging at once for example. That's very difficult to model so I'm probably just going to ignore it for now. Are there any other cost factors people think I should include?