MBTA "Transformation" (Green Line, Red Line, & Orange Line Transformation Projects)

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
I figure the following multi-year, committed, multi-billion projects are worth a collective thread:
GLT Green Line Transformation (https://www.mbta.com/projects/green-line-transformation)
RLT Red Line Transformation (https://www.mbta.com/projects/red-line-transformation-program)
OLT Orange Line Transformation (https://www.mbta.com/projects/orange-line-transformation-program)

I figure that they might each deserve their own thread (they're bigger, dollar-wise, than the Green Line Extension), but they'll unfold slow-enough and simultaneously enough that they seem to go together.

BLT (Blue Line Transformation) is not a declared thing as something of an accident of history: Blue Line completed its platform extensions and fleet renewal "early" and the only transformative project now is the extension to MGH (and elimination of the Bowdoin Loop). See "MBTA Red Line / Blue Line connector" thread

The Green Red Orange Transformations share a common theme and purpose: Capital Projects that increase capacity on the core lines through:
  • Signal improvement (faster trains, spaced closer together)
  • Track & Tunnel upgrades (less slow track; GLT adds changes to handle longer, standard cars)
  • Yard & Shop upgrades
 
Last edited:

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
Orange Line Transformation is:
  • Orange Line signal upgrades: Design started in 2019
  • New Orange Line vehicles: First set of new cars in service August 14, 2019; more in testing
  • Wellington Yard and Maintenance Facility updates: Work started in summer 2017 for the maintenance facility, and spring 2018 for Wellington Yard
The following projects are now complete:
  • Rehabilitation of Orange Line test track: Completed summer 2018
  • Storage track expansions at Wellington Yard: Completed spring 2019
 

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
Red Line Transformation includes:
  • Red Line signal upgrades: Design started in 2019
  • New Red Line vehicles: Vehicles ready for buildout in Springfield, MA in summer 2019
  • Red Line test track: Scheduled to be complete by winter 2020
  • Cabot Yard Maintenance Facility: Work began in summer 2019
 

Equilibria

Senior Member
Joined
May 6, 2007
Messages
6,425
Reaction score
6,352
There are actually two more (based on FMCB meetings): Fare "Transformation" (formerly known as "AFC 2.0") and Bus "Transformation" (formerly known as "Bus Network Redesign" and "Better Bus Project"). I think this is silly, but it's become a buzzword.
 

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
Green Line Transformation has a cool program map for more information.

Service Improvements
Infrastructure Improvements
 
Last edited:

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
Also, I'm expecting to discuss the vehicles as part of the existing vehicle-procurement threads:
New Red and Orange Line Cars

There are actually two more (based on FMCB meetings): Fare "Transformation" (formerly known as "AFC 2.0") and Bus "Transformation" (formerly known as "Bus Network Redesign" and "Better Bus Project"). I think this is silly, but it's become a buzzword.
Good point.
For the Bus (including the "better bus stuff" and Bus Transformation we haveL
MBTA Bus & BRT

For Fare Transformation we have:
MBTA Fare System (Charlie, AFC 2.0, Zone, Discounts)
 

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
RLT promises capacity for 65,000 additional daily riders, which is about a 25% increase over ridership that bounces around 270,000.

I'm kind of surprised that OLT promises only +30,000 (on a current 200k).
 

Arlington

Moderator
Staff member
Joined
Dec 10, 2011
Messages
5,547
Reaction score
2,556
Here's one I don't get: Why they need to keep the Park Street loop as is? Why not make it a 49 footer (matching Brattle Loop at Gov Center) by putting "short turns" onto the *outside* (leftmost) track instead of trying to put it on the inside? Gentle loops are quieter and less likely to cause derailment. (Is there an "industry standard" difference worth accommodating, at, say 48 ft?) Also the ability to send trains from the inside track on the inbound platform is long overdue. As it is, you can't unload 2 inbound trains at Park unless you're willing to turn one and send it back out.
 
Last edited:

F-Line to Dudley

Senior Member
Joined
Nov 2, 2010
Messages
8,446
Reaction score
5,598
Too many support beams to move to modify Park Loop. It's within tolerance for most modern LRV's, so a matter of not making a mess where a mess doesn't need to be made. The thru-service crossover is the big gain for being able to wave Lechmere trains ahead of GC-turning trains en route to GC. That's a huge one for congestion management.
 

Riverside

Senior Member
Joined
Mar 19, 2012
Messages
1,266
Reaction score
2,151
Big +1 for the consolidated thread (with links to other threads as relevant). Great information here!
 

bakgwailo

Senior Member
Joined
Apr 15, 2016
Messages
1,513
Reaction score
896
Isn't the Mattapan Highspeed Line work officially a "transformation" project now, too?
 

Andrew

New member
Joined
Dec 19, 2019
Messages
32
Reaction score
32
Regarding the Park St loop, has anyone (MBTA or otherwise) explored how catastrophic it would be to just get rid of the loop entirely and just redirect trains after GC? That loop seems to be a lot bigger on maps and isn't so much father away that I could see the extra few minutes impacting quality of service.
 

The EGE

Senior Member
Joined
Jun 29, 2013
Messages
1,415
Reaction score
3,008
Park Street loop can, and should, go. It's by far the worst curve on revenue trackage. GLX will vastly reduce the number of trains that need to turn in the downtown core - especially if the Medford Branch exceeds projections before the Type 10s arrive, in which case the C will need to be through-run as well.
 

Equilibria

Senior Member
Joined
May 6, 2007
Messages
6,425
Reaction score
6,352
Park Street loop can, and should, go. It's by far the worst curve on revenue trackage. GLX will vastly reduce the number of trains that need to turn in the downtown core - especially if the Medford Branch exceeds projections before the Type 10s arrive, in which case the C will need to be through-run as well.
If the Type 10s can be off-shelf while keeping it, why decommission it?
 

The EGE

Senior Member
Joined
Jun 29, 2013
Messages
1,415
Reaction score
3,008
The short answer: they can't. Standard radius for off-the-shelf vehicles is 82 feet (25 meters), with some models at 66 feet (20 meters) or 59 feet (18 meters). Anything below that (especially in/near revenue service - fully non-revenue yard areas can sometimes have smaller radii at highly restricted speeds) is a custom model. Park Street loop is the only difficult and frequently-used curve to get to that 59-foot radius; everything else is either going away (Lechmere), rarely used (Kenmore Loop, Brattle Loop), easy to fix (Heath Street, Cleveland Circle, the BC yard loops by moving the platform to the median), or deep in Riverside or Reservoir yards.
 

F-Line to Dudley

Senior Member
Joined
Nov 2, 2010
Messages
8,446
Reaction score
5,598
The inner crossover installation at Park is worth enough congestion mitigation to allow B's to return to using GC loop full-time, so Park will again return to being without a regular revenue service pattern. That'll help, but even all those years things weren't regularly turning at Park the loop was still needed on daily as-needed basis as a bail-out for delays before they cascaded too thoroughly to GC. That's the dilemma they'd face in getting rid of it. It's a lot easier during a delay recovery sequence to yank stuff as-directed at Park while it's still on the 4-track portion instead of gambling on too many past-GC trains that need the far-end platform berth getting stuck behind turning GC trains that need the inner platform berth. The inbound thru-service crossover at Park should greatly improve this situation as regular practice will now put all past-GC trains on one track (probably the current thru track) and all turning trains on the fence track with prioritized signaling giving past-GC trains chance to jump ahead of the turning train and hit their far-end platform spot without having to wait. It'll mean, besides B's being able to turn at GC again instead of Park, that the turning trains may have to frequently wait a few seconds longer for schedule adjustment before leaving Park so the next thru train can queue-jump. But it'll also mean there'll be less schedule adjustments writ-large on the Central Subway because the Park-GC segment will be able to handle so much more throughput with so much better congestion mitigation options...thus making those schedule adjustments less frequent and irritating overall.

The question is: is that enough unto itself to retire Park Loop? As big an improvement and as better the resilience that crossover affords, it's not going to completely zero-out the need to throttle turning traffic in a delay recovery scenario. So they do have a viable point that retaining Park Loop is vital for operational flexibility, even without the brittleness of before and without any daily service pattern utilizing it. The only debate is whether retaining a 47 ft. radius loop as revenue track hoses the off-shelf buying options to a degree that clobbers what they end up paying in unit price for the new fleet. Custom dimensions are not necessarily evil if they can be done as adaptation to an off-shelf model, staying fully in their lane at leveraging a generic supply chain. It's different if the whole ground-up design has to be unique-to-Boston and you start having to do things like custom trucks yet again. The GLT task force hasn't spelled out yet exactly where that threshold is between light customization of a generic design and divergently-custom design re: these borderline-radius curves. We don't have specific enough info to make that call to toss Park Loop at any cost, or keep at all (reasonable) cost because the bail-out option is still needed for delay recovery or some future expansion branch pattern might end up needing to use it as a regular turnback. And Brattle Loop too is going to be a tricky one because of the near certainty that GLX-Medford is going to need some part-time rush hour short-turning augmentation there at the kind of ridership its likely to generate, as well as any Urban Ring LRT hook-ins from Lechmere likely needing to use that loop as a permanent all-day turnback. Curve tolerances vs. buying options and where the cost-escalator thresholds are are one of the things they're going to have to spell out in more detail in future FCMB presentations.
 
Last edited:

Equilibria

Senior Member
Joined
May 6, 2007
Messages
6,425
Reaction score
6,352
Asking a probably stupid question - is there no way to install a switchover between Park and Boylston to allow the train to simply reverse direction at Park? The T only uses 1 of 2 Lechmere-bound platforms as it is (and the one they don't use is currently dedicated to the loop) so having the train wait long enough for the driver to run to the other end seems plausible...

It's generally weird to me that the T would keep any loops, and they're going to an in-reverse-out model at Boston College. Why not here?
 

Top