While they are not keeping the project website up to date at all, the second largest DOT contract (I-495/I-90 interchange the largest) is ongoing in Weston/Newton.
Presentation from March when it was at the MassDOT Board for approval.
The Newton-Weston I-95/I-90 Bridge Bundle project is replacing 4 bridges, rehabilitating 3 bridges and replacing the superstructures on 2 additional bridges for a total of 9 bridges at the interchange. Awarded to a JV team SPS-Walsh, which is a Joint Venture of SPS New England Inc of Salisbury and Walsh Construction Co of Chicago the project will take 4 1/2 years to complete with final completion in 2028.
The bridges include.....
1) I-90 over the Charles River/I-95/Ramps A/B- Full bridge replacement of entire structure with new structure to be built slightly to the East and within existing footprint with 5 traffic stages
2) I-90 over MBTA Worcester Commuter Rail- Superstructure Replacement to be completed over 55-hour weekend lane shifts on I-90 with full barrel closures & zipper barrier.
3) I-90 over Charles Street- Bridge Rehabilitation
4) Ramps A/B over Charles River (from I-95 NB to I-90 Former Toll Area)- Superstructure Replacement
5) Ramps A/B over I-95/Charles River- Bridge Rehabilitation
6) Ramp G over Ramps A/B/ Former Toll Area (from I-95 SB to I-90 EB)- Full Bridge Replacement, to be built off-line on new alignment
7) Ramp G over Hultman Aqueduct- Full Bridge Replacement, to be built off-line on new alignment
8) Ramp G over I-90/Ramp K- Full Bridge Replacement, to be built off-line on new alignment
9) Ramp C (I-90 Former Toll Area to I-95 SB) over Hultman Aqueduct- Bridge Rehabilitation
First major traffic shift took place last weekend where traffic was shifted off the C-D road that takes traffic from I-90 or Grove Street onto I-95 NB. The lanes and the ramps are now shifted out to the mainlines (but still separated on I-95 NB) on a new temporary roadway crews built. This gives crews a work zone to set up a crane.