Latest update on South Station construction progress (from the project managers); bold-face added for emphasis:
Activity on Tracks and Platforms
Activity on Tracks and Platforms
- The contractor is currently erecting a steel structure that will cover the entire railyard, which will support the expanded bus terminal. The new structure currently covers Tracks 1-12. The contractor will continue to place concrete on the steel structure, above the tracks, as it is completed.
- The existing platform canopies are in the process of being removed during the overnight shifts. Crews are currently working to remove the canopy over Tracks 6 & 7 and will move sequentially until all canopies are demolished. This work should be completed in the next few months.
- Crews continue to work at night in the railyard to begin fireproofing installation. This work may modify the paths of travel at the ends of the tracks during the overnight hours.
- A second crane, located between the station and the Post Office (adjacent to Track 13), is erecting the east side of the expanded bus terminal. Due to this work, Track 13 is out of service. This crane will be demobilized in the coming weeks, and a smaller crane will take its place to complete the steel erection over Track 13 this fall.
- In the Tower Work Zone, work continues on the concrete foundation for the tower. This concrete cap beam is expected to take 2 more weeks to complete.