The "last panel" refers to the last to be installed by the tower crane. The crane will come down in late May. But the material hoists (elevators) on the outside of the building will remain until the interior elevators are complete and approved for operation (hopefully around August). Only then can the hoists will be removed, and a mobile crane will come to install the remaining panels on the west facade. You will see in the coming days, work on the granite and brick "base" facade will begin. Currently we are on track to complete the building and move-in our first tenants around the first of next year (Jan 2024).
Jonathan