- Joined
- Jan 7, 2012
- Messages
- 13,981
- Reaction score
- 22,075
1) drive steel or concrete piles to bed rock or at least the deep marine or glacial clay -- the approach of the Pru & Hancock
2) build slurry walls or drive sheet piles then excavate and pour a thick slab -- the approach of the MIT Student Center -- essentially your basements are the hull of a boat
3) drive wooden piles into the mud and then set your building on top -- the approach of Richardson for Trinity Church
From what seems to be happening -- it looks like it could be #2 with a pit to be excavated and a mat to be poured.
FYI:
The perimeter steel sheeting is already installed to allow earth retention for the excavation. These steel piles are the column supports. After driving these piles, the site will be excavated to below the garage level, then concrete will start at the bottom and work up.
Please note photos shown in #'s 34 and 38 of this thread.MotoB -- I see cranes and steel sticking out of the ground -- I don't see a pile driver
Please note photos shown in #'s 34 and 38 of this thread.
I really don't know much about what different pieces of construction equipment do, but the crane in my photo (post #45) has an attachment on it that was definitely drilling, or at least pushing down into the ground.
Mat and Moto thanks for the information. It's nice to know what I've been looking at.
Thanks, much appreciated.
So as of today, Jan. 9, they have the site surrounded with water cutoff piles to the west and steel sheeting other 3 sides. They are driving (vibrating) all the 140-foot steel H-piles from grade. When done, they will excavate about 20 feet down, cutoff the piles and make concrete pile caps, grade beams, walls and a basement slab. They will then form the walls and columns for each floor of concrete for 27 floors.
It IS a historic landmark, being the location of the famous Ted fight scene. https://www.youtube.com/watch?v=YoT9pSlsV7E
Moto: Now that I look closely at the most recent photo -- I can see the "vibratory Hammer" as an appendage hanging from the larger crane
Are the H sections being welded or bolted to reach the bedrock level?
Keep the updates coming -- its great to have someone who is either on-site, or has access to actual information instead of rumour and speculation
No pics, but I saw today a couple of these beams that appeared to be a solid 50' in the air, while most of the others were only maybe 5' out of the ground. Does that just mean they were in the process of being (vibration) hammered in? There wasn't any equipment or work being done at that particular second, so I found it a little odd to see those 2 beams.