January-March 2018 Progress
Thursday, May 3, 2018
During the past three months, we finally have moved past the complicated structural belt truss structural system and have poured concrete for levels 29-48. Curtainwall installation has been completed up to level 29 and continues to wrap the building at a steady pace. The ground level exterior granite facade begun and continues to be installed on the podium facade around the curtainwall. Almost all the steel canopy outriggers are in place. The exterior hoist is now running up to level 40. The drywall/finishes have progressed up to level 18 in the hotel. Service elevators fronts and cabs have been installed. MEP rough in has progressed from the hotel floors to the residential floors up to level 28. Testing on level 25 MEP equipment is in process.
The next 3 months include the following activities:
- Concrete Structure – Level 49-61
- Hoist access – Up to Level 55
- Curtainwall – Up to Level 41
- Core Elevators – Railings installed to Level 52
- Exterior facade stone continue installation
- GAS and DAS Utilities into the building
- 1st and 2nd MEP Floor Rough progressing
- MEP Rough in – Up to Level 36 (Residential)
- Drywall/Finishes – Up to Level 27 (Hotel)
- Elevator Lobbies Rough and Finishes to level 24
- B2 NSTAR Room Energization Complete
- B2 Kitchen Complete