Its my understanding there won't be much visible progress over the next month-and-a-half to two months.
Their goals through March on the site as of 12/2016 are:
So 3 floors in 3 months. Things are going to be slow for just a bit longer, then it will shoot up.
http://www.1daltonconstruction.com/single-post/2016/12/28/November---December-2016-Progress
Their goals through March on the site as of 12/2016 are:
- Finish pouring the concrete slab for the ground floor
- Install preliminary drains, piping and waterproofing at ground level for future landscaping and utility work
- Frame and prepare for concrete slab pour for ground floor shear walls, 2nd floor slab and shear walls and 3rd floor slab and shear walls
- Install the climber for concrete pours
So 3 floors in 3 months. Things are going to be slow for just a bit longer, then it will shoot up.
http://www.1daltonconstruction.com/single-post/2016/12/28/November---December-2016-Progress