1.10.3 Schedule
The Proponent has developed both a Phasing Plan and a Construction Schedule designed to take advantage of construction efficiencies. Upon completion of Blocks A, H and J (Phase 1), the remaining Project will be built on a series of large “bathtubs” with below-grade floor plates for parking and access. Each bathtub will serve as the foundation upon which multiple buildings will then be constructed. Considerable construction efficiencies will be realized by constructing these bathtubs sequentially.