During the these past two months, the concrete for floors B3-B1 was completed. A secondary crane was also installed to help move materials on the site. The ground floor concrete will also be nearly completed during this time.
Some of the highlights for the next 3 months are:
- Finish pouring the concrete slab for the ground floor
- Install preliminary drains, piping and waterproofing at ground level for future landscaping and utility work
- Frame and prepare for concrete slab pour for ground floor shear walls, 2nd floor slab and shear walls and 3rd floor slab and shear walls
- Install the climber for concrete pours
Behind the scenes the project team continues to coordinate the work required to continue the rise of One Dalton into the Skyline.